A global Tier-1 supplier of automotive seating systems was planning new assembly lines for several international production sites. Growing product variety and fluctuating OEM call-off quantities placed high demands on production stability and efficiency.

The central question was how many buffer positions were really needed, and when a synchronous or asynchronous assembly line would be appropriate.
The challenge
Seat assembly proceeds through a sequence of workstations. Different variants, customer-specific equipment and short-term programme changes can cause cycle-time deviations and production peaks.
The planning team needed to determine the appropriate line structure, whether buffers were necessary between every station, the floor space required and the location of actual bottlenecks. Conservative sizing would increase investment and space costs; insufficient buffers could threaten delivery performance.
🎯 The objective
The project sought a balance between investment and line performance: stable production despite a high variant mix, the minimum necessary buffer capacity, efficient use of floor space and a sound basis for international line roll-outs.
The approach
A detailed Simio model was built using actual production data. Scenarios covered different order and variant mixes, synchronous and asynchronous lines, the number and location of intermediate buffers, and effects on throughput, utilisation and changeover times.
The scenarios were assessed using output, floor-space requirements, line performance and investment requirements.
💡 Customer benefits
The project supported investment decisions for new assembly lines, reduced floor-space requirements for the same output, stable operation despite product variety and a repeatable planning approach for international plants. It helped the supplier move from experience-based assumptions to a data-based decision process.