How many injection moulding machines can operate usefully when downstream capacity is limited? This project example shows a Simio model of plastic parts production with up to 48 injection moulding machines, an intermediate buffer and several finishing stages.
The central question was:
Which combination of active injection moulding machines, finishing capacity and shift patterns provides high output without excessive inventory and congestion?

🧩 Challenge
The output of individual moulding machines does not determine the throughput of the entire process. If upstream production exceeds finishing capacity, inventory grows in front of the buffer. In practice, this can overload available space and cause congestion back to the moulding machines.
- How many injection moulding machines should be active?
- Are two tumbling machines sufficient, or are four needed?
- How should shift patterns for moulding and finishing be coordinated?
- How much inventory builds up inside and in front of the rack?
- Which configuration combines high output with manageable intermediate inventory?
🎯 Objective
Align capacity and operating hours across the entire process chain. The focus was high total output with limited buffer inventory, providing a basis for selecting suitable machine and shift configurations.
🏭 Modelled production process
- Injection moulding: up to 48 machines produce plastic parts, collected in boxes of 50,000 pieces.
- Quality inspection: sampling of manufactured parts.
- Buffering: a storage rack holds nine boxes; inventory in front of the rack is recorded separately.
- Tumbling and separation: finishing on two or four tumbling machines, followed by separation on two machines.
- Packaging and labelling: parts are packed into bags of 10,000 pieces and labelled.
⚙️ Approach
Input data is imported from MS Excel, allowing parameters and alternatives to be changed without rebuilding the model. Random effects include machine failures and variation in the number of parts produced per injection shot.
A Simio experiment combines the following settings:
- number of active injection moulding machines
- two or four tumbling machines
- shift pattern for the remaining machines
- a separate shift pattern for tumbling
The shift alternatives shown are 24 hours from Monday to Friday and 20 hours at weekends, or 16 hours every day. Each scenario is run ten times with different random number streams. The mean results are then compared.
🎬 Model and results in the project video
The video demonstrates model controls, material flow from injection moulding to finished bags, and comparison of experiment results.
📊 Evaluation: assess output and buffers together
The experiment records processed boxes and maximum inventory inside and in front of the rack. The video results show why ranking configurations by output alone is insufficient:
| Measure | Scenario A | Scenario B |
|---|---|---|
| Active injection moulding machines | 48 | 48 |
| Tumbling machines | 4 | 4 |
| Shift pattern for the other machines | Mon–Fri: 24 hours/day; Sat–Sun: 20 hours/day | Mon–Fri: 24 hours/day; Sat–Sun: 20 hours/day |
| Shift pattern for tumbling machines | 16 hours every day | Mon–Fri: 24 hours/day; Sat–Sun: 20 hours/day |
| Processed boxes | 3,152.1 | 3,142.1 |
| Mean maximum inventory in the rack [boxes] | 9.0 | 6.5 |
| Mean maximum inventory in front of the rack [boxes] | 95.8 | 1.1 |
Almost identical output can be associated with very different intermediate inventory. Simulation reveals this trade-off: selecting a configuration requires considering buffer load and congestion risk alongside output.
💡 Customer benefits
- Plan capacity as a system: coordinate moulding and finishing rather than sizing each stage in isolation.
- Identify buffer risks early: reveal inventory build-up before it disrupts real operations.
- Choose shift patterns on a sounder basis: compare the system-wide impact of different operating hours.
- Prepare investments more effectively: assess how much additional equipment contributes to total output.
- Repeat scenario comparisons: use Excel inputs and Simio experiments for transparent what-if analysis.