A medium-sized packaging manufacturer wanted to improve internal logistics. Increasing transport effort and high forklift leasing costs prompted a review of the existing layout. The main questions concerned the location of a new buffer rack system and the potential to reduce forklift numbers.

The challenge
Production structures that had grown over time caused inefficient flows between storage, production and shipping. The team needed to assess new storage and buffer locations, forklift assignments to production zones, excessive travel and the actual number of leased forklifts required.
The objective
The project sought shorter routes, lower forklift and leasing costs, suitable positioning of storage and production areas, and stable material supply.
The approach
Working with the customer, we built a Simio model from actual production and transport data. Scenarios compared rack positions, buffer locations, forklift numbers and assignments to production areas. Measures included distance travelled, resource utilisation and operating costs.
📊 The result
The simulation identified layout and resource arrangements with lower transport effort and reliable production supply. Structural causes of unnecessary travel could be addressed. The project reported significantly shorter routes and an almost halved requirement for leased forklifts, alongside appropriately located buffers and a supported layout decision.