A large electronics manufacturer needed to manage orders efficiently through a multi-stage printed circuit board production process. Product variety and changing priorities were increasing work in progress and setup effort. The central question concerned the order sequence that would improve delivery performance while reducing inventory and setups.

The challenge
Boards pass through many processing steps. Queues before individual stations increased lead times and inventory. The team needed to understand the effects of release strategies and priority rules on delivery performance, throughput, inventory and setups, and identify a stable control approach.
The objective
The targets were reliable customer delivery, lower work in progress, less setup effort and stable output across the process stages.
The approach
A Simio model of the complete process was combined with multi-stage optimisation. Strategies included FIFO control, priority-based ranking and dynamic prioritisation with maximum permitted waiting times. Evaluation used delivery performance, work in progress, output and the proportion of setup time.
📊 The result
Combining Simio simulation with its optimiser identified a suitable job release strategy. The reported benefits included better delivery performance, lower work in progress and setup effort, stable higher output and faster, informed decisions.