Project: resources and capacity in parcel sorting

A parcel logistics company assessed staffing, swap bodies and transport vehicles for normal operations and seasonal peaks.

An international logistics company operating several parcel sorting centres needed to handle sharply rising seasonal volumes, especially before Christmas. It wanted to establish which delivery promises could be met and the staffing and equipment required.

Project example: Resource and capacity planning for a parcel sorting center

The challenge

Peak volumes increase quickly while delivery-time commitments remain demanding. Permanently oversized resources would be expensive. The company needed to assess staffing by work area, swap bodies and transport vehicles, peak sorting capacity and the balance between investment and performance.

The objective

The aim was reliable delivery performance and stable peak operation with economically sized staffing and equipment.

The approach

A Simio model of the sorting centre compared normal and Christmas operations, different parcel volumes, staffing levels by process area, and numbers of swap bodies and vehicles used to move them. Measures included performance, costs and delivery reliability.

📊 The result

The model clarified the resources needed to maintain stable processes and meet promised delivery times during peaks. The project supported an economical balance between investment and operating performance, appropriately sized resources, avoidance of unnecessary overcapacity and a sound capacity planning basis.

We can discuss a similar seasonal planning question in a free initial conversation.

Let’s talk about your processes